The Contractor shall commence the execution of the Works as soon as is reasonably practicable after the Commencement Date, and shall then proceed with the Works with due expedition and without delay.
承包商应在开工日期后合理可行的情况下尽快开始实施工程,随后应迅速且毫不拖延地进行施工。
2
We undertake, if our bid is accepted, to commence the WOEKS and to complete and deliver the whole of the WORKS within the time stated in the Exhibit C of the draft document.
如果我们的投标被接受,我们将开始工作,并承诺按分包合同草案附表C所列的时间完成并交付整套工程。
3
Ensure and take the necessary safety measures before the renovation workscommence.