This paper presents a design example of using a cable crane for lifting and erecting an access bridge for the right bank spillwaytunnel for the Lubuge Hydropower Station.
这里介绍了应用于鲁布革右岸泄洪洞交通桥吊装的缆索起重机的设计实例。
2
There is adverse spatial stress distribution at the end of the plug of diversion tunnel, which is to be transformed into permanent spillwaytunnel.
由导流洞改建而成的永久泄洪洞,在堵头末端存在导流洞与泄洪洞交汇的不利情况。
3
In order to monitor project's safety status of every section it is designed to arrange some interrelated instruments at slope dam spillway and diversion tunnel.