If activity of any system component is increasing throughout the test run, the system has not reached steadystate.
如果任何系统组件的活动在测试运行过程中增加,则系统不会达到稳定状态。
2
The test plan can be configured to produce a steady-state workload or to introduce variability by alternating the load between multiple virtual machine groups.
配置测试计划来产生状态稳定的工作负载,或者通过调整多个虚拟机组之间的负载来产生变化。
3
During the steadystate for the run we averaged about 1.5 million Lotus Domino transactions every 10 minutes during the test or about 9 million Lotus Domino transactions per hour as shown in figure 8.