Upon receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine this cost, which shall be included in the Contract Price.
在接到通知后,工程师应依据第3 . 5款【决定】,对此费用作出商定或决定,并将之加入合同价格。
2
However, unless otherwise agreed by both Parties, the Engineer shall not delegate the authority to determine any matter in accordance with Sub-Clause 3.5 [Determinations].
但是工程师不能授予其按照第3.5款【决定】的规定决定任何事项的权力,除非合同双方另有协议。
3
The Sub-Contractor shall employ a qualified surveying engineer for this purpose, whose suitability (training certificate) is to be produced if requested by the Contractor.