This Paper introduced structure reform for mainsteampipe of heat and power plant at a Petrochemical factory.
本文简述了某炼油厂热电站主蒸汽母管的结构改造和动力设备的调优运行。
2
There were some analysis and probe of creep in mainSteampipe and reheat pipe (hot segment) in service utility boiler.
对目前在役的高压电站主蒸汽管道和再热汽管道(热段)蠕变现象进行了分析与探讨。
3
The method of through monitoring 16N activities in the mainsteampipe to get the leak rate of steam generator, now is the main way of steam generator leak rate monitoring.